Activities Planned for Last Week:

  • Complete GUI
  • Begin formal testing
  • Draft of ppt
  • Present project prototype to industry professionals
  • Store code snippets to file
  • Integrate prototype with RATS

Activities Accomplished Last Week:

  • Begin Testing
  • Draft of ppt
  • Present project prototype to industry professionals
  • Store code snippets to file
  • Update prototype with RATS

Activities Planned for Next Week:

  • Formal Testing
  • Bring program to first Beta
  • Presentation Work
  • Documentation

New Issues:

  • How to store vulnerability info with line number/varaible
  • Line number changes from source code and file RATS will scan

Old Issues:

  • RESOLVED: Hierarchical tree for GUI